Production Journey
The Path to Craftsmanship
An average 14-week production journey, from technical evaluation to final quality control and export handling.
Timeline
Week 1 - 2
Phase 01
Initial Evaluation & Scheduling
- 1Technical & design evaluation
- 2Cost generation and approval
- 3Purchase Order
- 4Production Scheduling
Timeline
Week 3 - 7
Phase 02
Material Sourcing & Preparation
- 1Material Selection & quality control
- 2Sawmill and Kiln Dry
Timeline
Week 4 - 8
Phase 03
Component Machining & Assembly
- 1Component machining
- 2Assembling
Timeline
Week 7 - 11
Phase 04
Surface Sanding & Finishing
- 1Sanding
- 2Finishing
Timeline
Week 12 - 13
Phase 05
Final QC & Packaging
- 1Final QC from internal and customer’s QC
- 2Packaging and labelling
Timeline
Week 13 - 14
Phase 06
Export Handling
- 1Export Handling
Production Note
*Production time may vary for each product depending on complexity of the manufacturing process and shipping conditions.